When a cheaper substitution costs more

A lower unit rate is only the start of the story. The real comparison is net value across function, transition cost, whole-life cost and risk.

By the COREXION team·2 min read

A contractor proposes an alternative product. The rate is lower and the saving looks immediate. Before accepting it, a client needs to know what is being given up, and what the change will cost to make.

The hidden costs of switching

A substitution rarely affects one line of the BOQ. It can trigger redesign, resubmittals, cancelled orders, new testing and changes to the programme. Each of these carries a cost, and together they can erase the saving on the rate.

Then there is the life of the asset. A cheaper finish may need replacing sooner. A cheaper plant item may consume more energy or need more maintenance. These costs fall on the owner long after handover.

Compare on a common basis

We assess every alternative against the same four questions:

  1. 1.Function and quality: does it meet the required performance, specification, durability and warranty?
  2. 2.Capital and transition cost: what are the quantities, rates, redesign, cancellations, rework, testing and time effects?
  3. 3.Whole-life cost: what are operation, maintenance, replacement and residual value over an agreed study period?
  4. 4.Risk and benefits: what changes in supply, delivery and operation, and what risks remain?

The result is a net implementation value, not just a rate difference.

Rules that protect the client

Evaluation criteria are agreed before any option is scored. Removing a required function is treated as a scope change, not a saving. Every approved trade-off has an owner and a measure, so the benefit can be verified after implementation.

The right question is not "is it cheaper?" but "what is the net value, and what are we accepting?"
More insights

Further reading

PROJECT CONTROLS

Why lower payments alone don't prove savings

A project that is paying less this month is not necessarily spending less overall. Savings are proven by the forecast at completion, not by the cash curve.

COREXION team · 2 min readRead article›
HANDOVER

Completion, handover and readiness to operate are not the same milestone

A building can be physically complete and still not ready to open. Treating three distinct milestones as one is a common cause of late, disputed handovers.

COREXION team · 2 min readRead article›
CONSTRUCTION MANAGEMENT

Progress reports that mask exposure

A progress percentage can look healthy while cost and time risk build up underneath. Verified progress, based on accepted work, tells the real story.

COREXION team · 2 min readRead article›
Ready to discuss your project?
Get in touch with our team.
Let's talk ›